Environmental
Monitoring for 57 km long 138 kV Transmission Line Construction
Project, Fort St. John, BC
BC
Hydro and the British Columbia Transmission Corporation (BCTC)
retained EDI to establish and maintain a comprehensive environmental
monitoring program for the construction of a new transmission
line terminating at the new Fox Creek substation, approximately
50 km N-NW of Fort St. John. In order to facilitate the construction
work, and to ensure due diligence and compliance with all
legal and regulatory environmental requirements and expectations,
BC Hydro retained EDI to monitor all construction activities.
Francois
Lake, Sub-marine Transmission Line Installation Environmental
Monitoring, Burns Lake, BC
EDI
was retained by BC Hydro to conduct Environmental Monitoring
during the installation of a transmission line that was laid
across the bottom of Francois Lake. The specific work entailed
the monitoring of water quality during the open cut trenching
and concrete covering of the transmission line in the near
shore lake substrate areas. In addition, the Environmental
Monitor was responsible for the implementation of erosion/sediment
control works and site re-vegetation. An Environmental Monitoring
Report was submitted to BC Hydro at the end of the project.
Morfee
Mountain Transmission Line Installation Environmental Monitoring,
MacKenzie, BC
EDI
was retained by BC Hydro to conduct Environmental Monitoring
during the installation of an underground electrical cable
that provides power to communication towers on Mount Morfee,
northeast of Mackenzie, British Columbia. Sediment and erosion
control measures were implemented during and at the completion
of the construction activities
Morfee
Mountain Powerline Installation, MacKenzie, BC
EDI
was retained by BC Hydro to conduct a site visit and develop
an Environmental Management Plan (EMP) for the replacement
of an underground electrical cable that provides power to
communication towers on Mount Morfee, northeast of Mackenzie,
British Columbia. Sediment and erosion control measures were
identified for the construction activities associated with
the replacement of the cable.
Bridge
River Flow Ramping Fish Salvage Operations, Kamloops, BC
EDI
was retained by BC Hydro in 1997 to conduct fish salvage operations
on the Bridge River, downstream of the Terzaghi Dam, as part
of the 1997 Bridge River Flow Ramping Project. The primary
objective of this project was to capture live fish that would
otherwise be stranded during flow reduction events, thus reducing
mortality. All fish were identified by species, measured,
documented by capture locations, and returned to either the
Bridge River mainstem or Carpenter Reservoir.
