Industry
Training in Erosion and Sediment Control in BC, AB and YT
EDI
has delivered numerous erosion and sediment control training
courses and presentations to clients in multiple industry
sectors throughout BC, Alberta and the Yukon. In 2000, EDI
developed and delivered our own course in erosion and sediment
control. In 2002, we updated this course and delivered it
through the BC Forestry Continuing Studies Network. Since
2005, EDI staff members have also worked as instructors for
the erosion and sediment control course taught through the
Malaspina University-College Natural Resources Extension Program.
In total, EDI has trained over 1000 individuals in erosion
and sediment control.
Stoddard
Creek West Bypass Bank Stabilization Project, Fort St. John,
BC
CTL
Contractors Ltd. (CTL) retained the services of EDI to develop
an Environmental Management Plan (EMP) for a Ministry of Transportation
(MoT) slope stabilization project on the West Bypass Road
in Fort St. John, BC. The slope stabilization project involved
relocation of the former Stoddard Creek mainstem to an existing
side channel. Bioengineering techniques, including live bank
protection, live staking, and live palisades were used to
stabilize the new banks and enhance fish habitat within the
newly constructed channel. EDI designed and oversaw the design
and installation of these bioengineering works.
NEMI
Trend Small Coal Mine Erosion and Sediment Control Plans,
Tumbler Ridge, BC
EDI
was contracted by Northern Energy and Mining Inc. (NEMI) to
develop a surface erosion and sediment control plan for the
Trend Small Coal Mine, located approximately 35 km south of
Tumbler Ridge. The objective of the SEPSC Plan was to maintain
the water quality in the existing streams that flow through
and adjacent to the area of the mine site during startup construction
activities. The SEPSC Plan identified site-specific objectives
for Best Management Practices (BMPs), integrated within a
detailed construction sequence and work plan. EDI also provided
environmental monitoring during the construction phases of
the project.
Brule
Mine Erosion and Sediment Control Plan, Chetwynd, BC
EDI
prepared a surface erosion and sediment control plan for the
Brule Mine for inclusion in Western Canadian Coal Corp.’s
application under the BC Environmental Assessment Act. The
Brule Coal Mine is located in northeastern British Columbia,
approximately 50 km by road south of Chetwynd. Diversion and
sediment control structures were integrated into the mine
planning and design process for implementation during all
phases of construction and mine development.
Willow
Creek Coal Mine Sediment Control Plans, Chetwynd, BC
EDI was retained, on behalf of the Pine Valley Coal Corporation,
to design sediment and erosion control plans for the construction
and operation phases of the Willow Creek Coal Mine. The Willow
Creek Coal Mine is a thermal and metallurgical coal development,
situated approximately 45 km south west of the community of
Chetwynd, British Columbia, within the Pine Valley. The plans
identified potential erosion and sediment issues related to
the processing plant site, haul road and central pit, and
provide recommendations to minimize impacts to the environment
by mitigating erosion and sediment generated during the construction
and operation of the mine. EDI also provided environmental
monitoring service during the construction phases.
Swamp Point Aggregate Mine Erosion
Prevention and Sediment Control Plan, Stewart, BC
EDI
was retained by Ascot Resources Ltd. to prepare a detailed
Surface Erosion Prevention and Sediment Control (SEPSC) Plan
for Phase I Activities associated with construction and initial
operation of the Swamp Point Aggregate Mine. The Swamp Point
Aggregate Mine is located on the Portland Canal approximately
50 km south of Stewart, BC. The mine will crush, sort and
wash sand and gravel and then load the products into ocean
barges for shipment. The detailed SEPSC Plan provided an adaptable
and flexible approach for planning and implementing effective
erosion prevention and sediment control Best Management Practices
(BMPs) for mine, and provided detailed prescriptions for specific
activities associated with construction and initial operations.
Keg
Creek Tributary Streambank Restoration, Prince George, BC
Extensive
reconstruction of streambanks was required as a remediation
measure at three stream crossing sites near Prince George,
BC. Banks were successfully rebuilt using a variety of bioengineering
techniques involving both manual and machine installation
techniques.
Sustut
River Bridge Crossing-Site Assessment and Environmental Management
Plan (EMP) Preparation, north central BC
EDI
conducted a preliminary field assessment and prepared the
initial Environmental Management Plan (EMP) for a bridge structure
installation, proposed across the Sustut River in north central
BC. The EMP identified known and potential environmental issues
associated with the project plan. Focusing on a base case
design, the EMP addressed proper sequencing of construction
activities and provided recommendations for the use of erosion
and sediment control techniques during each phase of bridge
construction.